Case Study #3 Getting the Profile Needed
Parking structure job site with a broom finish concrete preparation need and additional two inches of concrete over the top of the existing substrate and required a CSP5 profile or greater. Blason Industrial used a Blastrac 2-20D shot blaster and paired it with the Blastrac 8-54DCGI Dust collector to remove traffic and parking stall lines while leaving behind the desired profile and accomplished this in one pass. Having the desired CSP5 profile concrete was ready for additional concrete pour, no down time waiting for concrete to dry or be cleaned.
Date: 6/7/2017
Location: Downtown Los Angeles, CA
Equipment Used: 2-20D Shot Blaster paired with 8-54DCGI Dust Collector
Company Name: Blason Industrial
Job Site Details:
20,000 sq. ft. of broom finish concrete preparation in a parking structure needing an additional 2 inches of concrete over the top of the existing substrate and required a CSP5 profile or greater. Machine was removing all traffic and parking stall lines while leaving behind the desired profile in 1 pass.